Für die Suche nach Inhalten geben Sie »Content:« vor den Suchbegriffen ein, für die Suche nach Orten geben Sie »Orte:« oder »Ort:« vor den Suchbegriffen ein. Wenn Sie nichts eingeben, wird in beiden Bereichen gesucht.

 

 

The test production of Olkiluoto 3 continuesZoom Button

Foto: Laitos Etualalla, Informationen zu Creative Commons (CC) Lizenzen, für Pressemeldungen ist der Herausgeber verantwortlich, die Quelle ist der Herausgeber

The test production of Olkiluoto 3 continues

The test production of Olkiluoto 3 continues

Sunday, August 28th, 2022

The automation updates at the Olkiluoto 3 (OL3) plant unit have been completed. The #test #production continues with tests at a power level of 60 percent. During this time, the plant unit produces approximately 850 megawatts (MW) of electricity to Finland’s national #grid between the tests. 

Automation updates were mainly carried out at the turbine, while some other updates also took place in the process automation on the reactor side. OL3’s regular electricity production, i. e., normal operation, is to start in December 2022.  

The test production programme’s remaining tests at a 60 percent power level consist of three main areas: the testing of moisture separation and reheating systems under various operational occurrence scenarios, function testing of turbine valves, and testing the planned change to house load operation. 

The purpose of the test production phase is to put the plant unit through different tests at varying power levels. According to the current production plan of the test production phase, tests at an 80 percent power level will take place in September and tests at full power in the beginning of October. The production forecasts may change due to the needs that emerge during the test production phase. Any needs for repair, maintenance, or inspection work identified in the tests are addressed during the test production phase. This ensures predictable and stable electricity production for the next 60 years.

The production forecasts can be followed here

Teollisuuden Voima Oyj has produced electricity for its shareholders, Finnish industrial and energy companies, safely and reliably for over 40 years. Nuclear electricity generated at TVO’s Olkiluoto plant covers approximately 30 percent of Finland’s electricity demand once Olkiluoto 3’s regular electricity production has started. Climate-friendly nuclear electricity not only benefits society but also reduces the environmental impact of energy production. Moreover, the world’s first final disposal facility for spent nuclear fuel is under construction in Olkiluoto.

TVO Online

Content bei Gütsel Online …

 

Fatal error: Uncaught TypeError: mysqli_num_rows(): Argument #1 ($result) must be of type mysqli_result, bool given in /pages/75/c9/d0016151/home/htdocs/domain-auf-schluer/include/content-browser.inc:249 Stack trace: #0 /pages/75/c9/d0016151/home/htdocs/domain-auf-schluer/include/content-browser.inc(249): mysqli_num_rows(false) #1 /pages/75/c9/d0016151/home/htdocs/domain-auf-schluer/index.php(986): include('/pages/75/c9/d0...') #2 {main} thrown in /pages/75/c9/d0016151/home/htdocs/domain-auf-schluer/include/content-browser.inc on line 249